County Hall, Portlaoise 3rd Floor
The contract involved major refurbishment of 3rd Floor, Block 1, County Hall, Portlaoise.
Construction consisted of steel frame with long span insulated panels. External facade consisted of curtain walling with rainscreen to the solid sections. Brise soleil fitted to southern elevation. Substantial mechanical and electrical works. Mechanical Services fitted over suspended ceiling. Electrical Services fitted under a raised floor system.
Other major work included the prevention of water ingress when existing roof was removed. Health & safety risks were high due to building operations being carried out above both pedestrian and vehicular circulation areas. This public building continued to operate as normal during the works.